24
Conservation of fuel and power
Approved Document L1A
L1A
QUALITY OF CONSTRUCTION AND COMMISSIONING
61 If satisfactory performance is not achieved,
then remedial measures should be carried out
on the dwelling and a new test carried out until
the dwelling achieves the criteria set out in
paragraph 60. In the period up to 31 October
2007, however if the initial test result on a
dwelling is unsatisfactory, reasonable provision
would be to:
a. carry out remedial measures such that on
retest, a result was achieved that showed:
i. an improvement of 75% of the difference
between the initial test result and the
design air permeability; or
ii. if less demanding, a test result within 15%
of the required design air permeability.
b. revise the TER by substituting the measured
air permeability obtained by following
paragraph 61a) for the value set out in
Appendix R of SAP2005, and demonstrate
that the DER is not worse than the revised TER.
This allows some time for builders to develop
the techniques for constructing to reasonable
standards of airtightness, but the poorer
airtightness will be reflected in the Energy
Performance Certificate, which will impact
on the value of the dwelling.
To illustrate the revised target following an initial
failure, if the initial test result was 18.0, and the
design air permeability was 8.0, the revised pass
level to reach in tests following remedial action
would be [18.0 – 0.75 x (18.0 – 8.0)] = 10.5m
3
/(h.m
2
)
at 50 Pa. However, if the initial test result was 9.5,
the pass level to be achieved in tests following
remedial action would be 8.0 x 1.15 = 9.2.
62 In addition to the remedial work on a dwelling
that failed the initial test, one additional dwelling
of the same dwelling type should be tested,
thereby increasing the overall sample size.
Alternative to pressure
testing on small developments
63 As an alternative approach to specific
pressure testing on development sites where
no more than two dwellings are to be erected,
reasonable provision would be:
a. to demonstrate that during the preceding
12 month period, a dwelling of the same
dwelling type constructed by the same
builder had been pressure tested according
to the procedures given in paragraphs 54
to 59 and had achieved the specified air
permeability.
b. avoid the need for any pressure testing
by using a value of 15m
3
/(h.m
2
) for the air
permeability at 50 Pa when calculating
the DER.
The effect of using this cautious value would
then have to be compensated for by improved
standards elsewhere in the dwelling design.
CRITERION 4 –
COMMISIONING OF HEATING
AND HOT WATER SYSTEMS
64 The heating and hot water system(s) should
be commissioned so that at completion, the
system(s) and their controls are left in the intended
working order and can operate efficiently for
the purposes of the conservation of fuel and
power. In order to demonstrate that the heating
and hot water systems have been adequately
commissioned, Regulation 20C states that:
Commissioning
20C.–(1) This regulation applies to building work
in relation to which paragraph L1(b) of Schedule
1 imposes a requirement, but does not apply
where the work consists only of work described
in Schedule 2B.
(2) Where this regulation applies the person
carrying out the work shall, for the purpose of
ensuring compliance with paragraph L1(b) of
Schedule 1, give to the local authority a notice
confirming that the fixed building services have
been commissioned in accordance with a
procedure approved by the Secretary of State.
(3) The notice shall be given to the local authority:
a. not later than the date on which the notice
required by regulation 15(4) is required to be
given; or
b. where that regulation does not apply, not more
than 30 days after completion of the work.
65 The procedure approved by the Secretary is
set out in the Domestic Heating Compliance Guide.
66 The notice should include a declaration
signed by a suitably qualified person that the
manufacturer’s commissioning procedures have
been completed satisfactorily.
One option would be to engage a member of an
approved Competent Person scheme.
App Doc L1A.indd 24
App Doc L1A.indd 24
28/3/06 17:25:06
28/3/06 17:25:06